Kinder Morgan (KM1 – KM6)
- Approximately 6.1 miles
- Pipeline Diameter: 66” to 84” (5.82 miles of 66” diameter to 0.25 mi. of 84” diameter).
KM1
- Pipeline Diameter: 66″ to 84″
- 0.9 miles in length
Anticipated Construction Program Schedule
DESIGN
Ended Spring 2021
BID
Late 2021 – Early 2022
CONSTRUCTION
Summer 2022 – Summer 2023
Design Consultant: Halff Associates
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM1
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
KM2
- Pipeline Diameter: 66″ to 84″
- 1 mile in length
Anticipated Construction Program Schedule
DESIGN
Ended Summer 2020
BID
Early 2022
CONSTRUCTION
Summer 2022 – Summer 2023
Design Consultant: IDS Engineering
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM2
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
KM3
- Pipeline Diameter: 66″ to 84″
- 1 mile in length
Anticipated Construction Program Schedule
DESIGN
Ends Summer 2021
BID
Summer 2022
CONSTRUCTION
Summer 2022 – Fall 2023
Design Consultant: Garver
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM3
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
KM4
- Pipeline Diameter: 66″ to 84″
- 1.1 miles in length
Anticipated Construction Program Schedule
DESIGN
Ends Summer 2020
BID
Fall 2021
CONSTRUCTION
Spring 2022 – Spring 2023
Design Consultant: LAN
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM4
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
KM5
- Pipeline Diameter: 66″ to 84″
- 1 mile in length
Anticipated Construction Program Schedule
DESIGN
Ended Summer 2020
BID
Spring 2022
CONSTRUCTION
Spring 2022 – Spring 2023
Design Consultant: Jones & Carter
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM5
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
KM6
- Pipeline Diameter: 66″ to 84″
- 1 mile in length
Anticipated Construction Program Schedule
DESIGN
Ends Fall 2021
BID
Fall 2023
CONSTRUCTION
Spring 2023 – Summer 2024
Design Consultant: Black & Veatch
Contractor: (To be determined)
PDF Map: SWSP – Kinder Morgan – KM6
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change