Central Pump Station
- Pipeline Diameter: 84″
- Located at N. Fry Road at Clay Road in Katy, Texas
Anticipated Construction Program Schedule
DESIGN
Ended Fall 2020
BID
Spring 2022
CONSTRUCTION
Winter 2022 – 2025
Design Consultant: AECOM
Contractor: Reytec Construction
PDF Map: SWSP – Central Pump Station
Contractor Notice to Proceed: November 2022
Project Completion: Fall 2025
Dates are subject to change