• Approximately 6.1 miles
  • Pipeline Diameter: 66” to 84” (5.82 miles of 66” diameter to 0.25 mi. of 84” diameter).

The Kinder Morgan segment is a 66-inch welded steel water line running along a Kinder Morgan pipeline corridor. The project was divided into six segments (KM1 – KM6) for construction. Construction of the Kinder Morgan Segments (KM-1 – KM-6), which are west of Fry Road to I-10 / Grand Parkway, will commence and be completed as a part of the 2025 conversion program and is expected to be completed by late 2026.

SWSP KM1 – KM6

KM1

  • Pipeline Diameter: 66″ to 84″
  • 0.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: Halff Associates

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM1

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM1

KM2

  • Pipeline Diameter: 66″ to 84″
  • 1 mile in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: IDS Engineering

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM2

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM2

KM3

  • Pipeline Diameter: 66″ to 84″
  • 1 mile in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: Garver

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM3

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM3

KM4

  • Pipeline Diameter: 66″ to 84″
  • 1.1 miles in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: LAN

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM4

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM4

KM5

  • Pipeline Diameter: 66″ to 84″
  • 1 mile in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: Jones & Carter

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM5

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM5

KM6

  • Pipeline Diameter: 66″ to 84″
  • 1 mile in length

Anticipated Construction Program Schedule

DESIGN

Complete

BID

Summer 2024

CONSTRUCTION

To be Determined

Design Consultant: Black & Veatch

Contractor: (To be determined)

PDF Map: SWSP – Kinder Morgan – KM6

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Kinder Morgan - KM6