Segment 3 (CenterPoint Corridor)

Approximately 13.8 miles of 42-inch-diameter pipeline.

SWSP Segment 3

The Segment 3 waterline is a 42-inch waterline that extends approximately 13.8 miles from Segment C (84-inch Waterline) near Brittmoore Road to the NFBWA Bellaire Pump Station along CenterPoint Energy (CPE) easements and some private easements. Segment 3 is being constructed in six separate construction packages.

Segment 3 will provide water to both NFBWA and WHCRWA customers via the Bellaire Pump Station.

The Segment 3 projects S3A-2 and S3A-4 are complete, and segments S3A-1 and S3A-3 are almost complete. Construction of S3A-5 and S3B 1 will commence and be completed as a part of the overall 2025 conversion program.

SEG3-A1

  • Pipeline Diameter: 42″
  • 2.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Summer 2020

BID

Spring 2021

CONSTRUCTION

Summer 2024

Design Consultant: Binkley & Barfield, Inc. (BBI)

Contractor: R Construction

PDF Map: SWSP – Segment 3 A-1

Contractor Notice to Proceed: October 2021

Project Completion: Summer 2024

SWSP - Segment 3 A-1

SEG3-A2

  • Pipeline Diameter: 42″
  • 2.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Summer 2020

BID

Spring 2021

CONSTRUCTION

Construction Complete

Design Consultant: Kimley-Horn

Contractor: E.P. Brady, LTD

PDF Map: SWSP – Segment 3 A-2

Contractor Notice to Proceed: June 2021

Project Completion: Summer 2024

Dates are subject to change

SWSP - Segment 3 A-2

SEG3-A3

  • Pipeline Diameter: 42″
  • 1.7 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Spring 2020

BID

Summer 2021

CONSTRUCTION

Summer 2024

Design Consultant: Freese and Nichols, Inc. (FNI)

Contractor: Main Lane Industries, Ltd.

PDF Map: SWSP – Segment 3 A-3

Contractor Notice to Proceed: September 2021

Project Completion: Summer 2024

Dates are subject to change

SWSP - Segment 3 A-3

SEG3-A4

  • Pipeline Diameter: 42″
  • 2 miles in length

Anticipated Construction Program Schedule

DESIGN

Ended Fall 2019

BID

Winter 2019

CONSTRUCTION

Construction Complete

Design Consultant: Costello

Contractor: Garney Construction

PDF Map: SWSP – Segment 3 A-4

Contractor Notice to Proceed: 12/12/2019

Project Completion: Early 2021

Dates are subject to change

SWSP - Segment 3 A-4

SEG3-A5

  • Pipeline Diameter: 42″
  • 1.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: Huitt-Zollars,Inc.

Contractor: (To be determined)

PDF Map: SWSP – Segment 3 A-5

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Segment 3 A-5

SEG3-B1

  • Pipeline Diameter: 42″
  • 2.9 miles in length

Anticipated Construction Program Schedule

DESIGN

Summer 2024

BID

Late 2024

CONSTRUCTION

To be Determined

Design Consultant: BGE, Inc. (BGE)

Contractor: (To be determined)

PDF Map: SWSP – Segment 3 B-1

Contractor Notice to Proceed: (To be determined)

Project Completion: (To be determined)

Dates are subject to change

SWSP - Segment 3 B-1