Segment 3 (CenterPoint Corridor)
Approximately 13.8 miles of 42-inch-diameter pipeline.
The Segment 3 waterline is a 42-inch waterline that extends approximately 13.8 miles from Segment C (84-inch Waterline) near Brittmoore Road to the NFBWA Bellaire Pump Station along CenterPoint Energy (CPE) easements and some private easements. Segment 3 is being constructed in six separate construction packages.
Segment 3 will provide water to both NFBWA and WHCRWA customers via the Bellaire Pump Station.
The Segment 3 projects S3A-2 and S3A-4 are complete, and segments S3A-1 and S3A-3 are almost complete. Construction of S3A-5 and S3B 1 will commence and be completed as a part of the overall 2025 conversion program.
SEG3-A1
- Pipeline Diameter: 42″
- 2.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Ended Summer 2020
BID
Spring 2021
CONSTRUCTION
Summer 2024
Design Consultant: Binkley & Barfield, Inc. (BBI)
Contractor: R Construction
PDF Map: SWSP – Segment 3 A-1
Contractor Notice to Proceed: October 2021
Project Completion: Summer 2024
SEG3-A2
- Pipeline Diameter: 42″
- 2.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Ended Summer 2020
BID
Spring 2021
CONSTRUCTION
Construction Complete
Design Consultant: Kimley-Horn
Contractor: E.P. Brady, LTD
PDF Map: SWSP – Segment 3 A-2
Contractor Notice to Proceed: June 2021
Project Completion: Summer 2024
Dates are subject to change
SEG3-A3
- Pipeline Diameter: 42″
- 1.7 miles in length
Anticipated Construction Program Schedule
DESIGN
Ended Spring 2020
BID
Summer 2021
CONSTRUCTION
Summer 2024
Design Consultant: Freese and Nichols, Inc. (FNI)
Contractor: Main Lane Industries, Ltd.
PDF Map: SWSP – Segment 3 A-3
Contractor Notice to Proceed: September 2021
Project Completion: Summer 2024
Dates are subject to change
SEG3-A4
- Pipeline Diameter: 42″
- 2 miles in length
Anticipated Construction Program Schedule
DESIGN
Ended Fall 2019
BID
Winter 2019
CONSTRUCTION
Construction Complete
Design Consultant: Costello
Contractor: Garney Construction
PDF Map: SWSP – Segment 3 A-4
Contractor Notice to Proceed: 12/12/2019
Project Completion: Early 2021
Dates are subject to change
SEG3-A5
- Pipeline Diameter: 42″
- 1.9 miles in length
Anticipated Construction Program Schedule
DESIGN
Summer 2024
BID
Late 2024
CONSTRUCTION
To be Determined
Design Consultant: Huitt-Zollars,Inc.
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 A-5
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change
SEG3-B1
- Pipeline Diameter: 42″
- 2.9 miles in length
Anticipated Construction Program Schedule
DESIGN
Summer 2024
BID
Late 2024
CONSTRUCTION
To be Determined
Design Consultant: BGE, Inc. (BGE)
Contractor: (To be determined)
PDF Map: SWSP – Segment 3 B-1
Contractor Notice to Proceed: (To be determined)
Project Completion: (To be determined)
Dates are subject to change